Acting Mayor of Archena, Andrés Luna, accompanied by municipal technicians, and the Director of Water of the Ministry of Agriculture, Andrés Martínez, have visited the works that are being carried out in the avenue Mario Spreáfico de Archena for its complete remodeling and adjustments .
In this artery of access to the population is running the project of installation of the Collector General Sanitation of the neighborhood of the Other Lao Archena.
This project has a financing of more than 240,000 euros.
That is to say, it is the placement, renovation and extension of the sanitation network of the entire avenue of Mario Spreáfico.
900 meters of ductile cast iron pipe for drinking water and 800 meters of PVC collector are being placed with the corresponding domiciliary connections, almost a hundred.
This is the first phase of a major project consisting of the complete remodeling of Mario Spreafico Avenue: pavement, sidewalks, as well as all street lamps.
Source: Ayuntamiento de Archena